Recovered planning appeal
If a planning application is refused permission, the applicant may lodge an appeal, which will usually be decided by a planning inspector acting for the Secretary of State.
However, planning appeals can be ‘recovered’ for decision by the Secretary of State. In this case the planning inspector prepares a report recommending how the appeal should be determined and passes this to the Secretary of State. The Secretary of State will then consider the inspector's recommendations and make a decision.
Appeals can be recovered at any stage of the appeal process, even after there has been a planning inquiry.
Appeals that are recovered tend to be:
- Those that relate to important projects of local significance.
- Proposals that give rise to regional or national controversy.
- Proposals that present novel issues or legal difficulties.
- Proposals that relate to the delivery of government policy or other government interests.
- Proposals relating to World Heritage Sites.
- Proposals relating to traveller sites in the green belt.
NB See Written statement by the Parliamentary Under-Secretary of State for Communities and Local Government (Mr. Parmjit Dhanda) June 2008 for more information.
Recovered appeals are determined in the same way as normal appeals, based on written representations, hearings or inquiries.
[edit] Related articles on Designing Buildings
- Called-in planning applications.
- Planning appeal.
- Planning Inspectorate.
- Planning permission.
- Planning related applications for judicial review.
[edit] External references
Featured articles and news
What it is and how to use it.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
The ECA Industry Awards 2024 now open !
Recognising the best in the electrotechnical industry.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.